Bituminous Road Information And Estimate | Road Construction Calculation

🛣️ Bituminous Road Information & Estimate

Complete construction calculation for a bituminous road (length 1500 ft, width 20 ft)
Bituminous road construction

📏 Road Parameters

📐 Length of road: 1500'-0"
📐 Width of road: 20'-0"
📏 Road Height: 1'-6"
⚙️ Edging: 3"
🌿 Site Dressing Width: 1'-0"
🧱 Sand Khoa Micro Layer (1:1) Height: 6"
🪨 Khoar Layer Height: 4"

📊 Detailed Quantity Estimate

#Item DescriptionFormula / CalculationQuantityUnit
1Soil Cut1500 × 20 × 1.545,000cubic feet
2Soil dressing1500 × 2030,000square feet
3Brick Flat Soling1500 × 19.5 (width after edging 20' - 3"×2 = 19'6")29,250sq. ft
4Herringbone Bond1500 × 19.529,250sq. ft
5Brick End Edging (both sides)1500 × 23,000feet
6Sand Microlayer (1:1) 6" thick1500 × 19.5 × 0.514,625cubic feet
7Feed Layer (Khoar) 4" thick1500 × 19.5 × (4/12) = 1500×19.5×0.33339,750cubic feet
8Bituminous Carpeting1500 × 19.529,250sq. ft
9Tack Coat1500 × 19.529,250sq. ft
10Seal Coat1500 × 19.529,250sq. ft
11Blinding on road with sand1500 × 19.529,250sq. ft
12Site dressing (both sides)1500 × 1 × 23,000square feet

📌 Note: For items 3 to 11, the width is taken as 19'-6" after deducting 3" edging on both sides (20' - 0'6" = 19'6").

📚 Related Civil Engineering Knowledge

🔬 Asphalt / Bitumen Testing Equipment

GOWE Asphalt Bitumen Dynamic Viscosity Tester

GOWE Asphalt/Bitumen High-Precision Dynamic Viscosity Tester

Brand: GOWE | Power Source: Corded Electric | Item Weight: 1 kg

Designed as per T0620 Asphalt Dynamic Viscosity Test (Vacuum Decompression Capillary Methods). Suitable for petroleum asphalt testing at 60°C, 300 mmHg vacuum. Measurement range: 4.2~580,000 Pa.s. Includes timing, temperature control, and data printing.

🛒 View on Amazon 🔍 Check more options

Popular

BariPlans chat with us on WhatsApp
Hello, How can I help you? ...
Click me to start the chat...